1. Give everyone the same brief

Prepare the property location, intended use, current condition, approximate size and the work you want completed. Add the available drawings, preferred style, budget range and target timing. Flag whether the space will be occupied during the work.

Without a shared brief, contractors may price different solutions. Comparing those figures can create the impression of a large saving when one proposal simply leaves out work included by another.

2. Ask for relevant examples and clear attribution

Look for examples with a similar property type and scope. Ask what the contractor actually delivered: design, joinery, installation, project coordination or the full package. Attractive inspiration images are different from evidence of completed work.

Where available and shared with permission, a relevant client reference can help you understand communication and delivery. Ask how changes were handled and what happened at handover, rather than focusing only on appearance.

3. Read the proposal as a working document

A proposal should make it possible to understand the work. Ask about vague descriptions such as “premium finish” or “complete interiors”. Which material, area and installation method do they refer to? What has not been included?

  • Identify drawings and material selections needed before execution.
  • Clarify owner-supplied items and who checks dimensions or compatibility.
  • Ask who coordinates any specialist trades involved.
  • Confirm the named point of contact and update arrangements.
  • Ask how a change is priced, approved and added to the programme.

4. Check the assumptions behind the schedule

A completion date is more useful when it is linked to a work sequence and decisions. Ask which materials need to be ordered early and which activities depend on access arrangements or approvals. Discuss what happens if an owner-supplied item arrives late.

Confirm the applicable property-management requirements directly for your building or community. Ask the contractor to explain who handles coordination and what information they need from you. Avoid treating a general promise about approvals as a property-specific plan.

5. Discuss completion before work begins

Agree how unfinished or defective items will be recorded, reviewed and closed out. Ask what product information, care instructions and any agreed warranty documentation will be provided. Keep the agreed responsibilities in the written scope.

Understand the proposed payment stages and what each stage relates to. If something is unclear, resolve it before appointing the contractor rather than relying on a verbal assumption.

Use the comparison to improve your own brief

Good questions often reveal that the brief itself needs refinement. You may discover a missing lighting allowance, an undecided finish or an access constraint. Update the brief and ask for any affected prices to be revised on the same basis.